M5 Westbound Upgrade

Utility relocation, street lighting and intelligent transport systems for the M5 Westbound Traffic Upgrade at Casula and Moorebank.

Roads & motorwaysPower
Principal contractorSeymour Whyte
Principal clientTransport for NSW (Endeavour Energy for the utility relocation package)
LocationCasula + Moorebank, Sydney NSW
StatusUtility relocation in delivery; street lighting and ITS awarded as at November 2026
SectorRoads & motorways

Project overview

The M5 Westbound Traffic Upgrade adds a new three-lane bridge over the Georges River and rail lines at Casula, a new Hume Highway entry ramp, modified M5 ramps, an upgraded Moorebank Avenue intersection and an upgraded shared user path.

Flomar has three packages with Seymour Whyte. Utility relocation is in delivery, relocating the 11kV, 33kV, LV and fibre network affected by the new bridge. The awarded street-lighting package covers the M5 corridor, Moorebank Avenue and Hume Highway. The awarded ITS package covers conduits, pits, poles, cabinets, cameras and traffic loops.

Flomar's scope of works

Utility relocation - in delivery

  • Removal of the existing de-energised overhead 11kV, 33kV, LV and fibre network including five poles
  • Open-cut trench or underbore installation of the replacement transmission and HV routes
  • Supply and installation of 11kV and 33kV cable, jointed to existing underground and overhead conductors
  • New poles, pole stay and underground-to-overhead connections
  • Electrical testing and digitised survey handover for network GIS updates
  • Permanent restoration of Powerhouse Road pavement and footpaths

Street lighting - awarded

  • Trenching, conduits and pits, with mandrel and rope proving
  • Underbores beneath roads and ramps, including send and receive pits and shoring
  • Bored piles and footings for street-light poles
  • Installation, electrical termination and commissioning of poles, outreach arms and luminaires
  • Cable hauling, jointing and termination, with connections to existing lighting cabinets and Endeavour Energy pillars
  • Removal of existing poles and luminaires, distribution boards on concrete plinths, testing and temporary trench reinstatement

Intelligent transport systems - awarded

  • Open trenching and underbores for conduits, draw rope, and rope and mandrel proving
  • Electrical, communications and pull-joint pits and lids
  • Footings for ITS poles, and plinths for distribution boards and roadside cabinets
  • ITS poles, distribution boards, roadside cabinets, pole-mounted enclosures and CCTV cameras
  • LV, fibre and loop-feeder cabling, with connections to existing switchboards and Endeavour Energy pillars
  • Vehicle-detection and traffic-signal coordination loops, with testing and commissioning of cabling, loops and equipment

Scope highlights

  • Utility relocation in delivery
  • Street lighting awarded
  • Intelligent transport systems awarded
  • 11kV and 33kV network relocation
  • Lighting poles, footings and cabling
  • ITS conduits, pits, cabinets and traffic loops

Project register

Principal contractorSeymour Whyte
Principal clientTransport for NSW (Endeavour Energy for the utility relocation package)
LocationCasula + Moorebank, Sydney NSW
StatusUtility relocation in delivery; street lighting and ITS awarded as at November 2026
ValueOn request

Value bands cover Flomar's own package only, never the whole-project figure, and are provided on request.