SYD08 Seven Hills Data Centre 33kV Supply

Civil works and cable installation for two new 33kV underground feeders supplying the Microsoft SYD08 data centre at Seven Hills.

PowerData centres
Principal clientAusconnex
LocationSeven Hills, NSW
StatusCompleted
SectorPower

Project overview

SYD08 is a new 33kV underground supply for the Microsoft data centre at Seven Hills in Western Sydney. Two feeders connect the Baulkham Hills Transmission Station to the data centre as it transitions from an 11kV supply to 33kV.

Flomar delivered the civil route and cable installation with Ausconnex on the Endeavour Energy network. The package covered trenching and shoring, conduits, joint bays, backfill and compaction, asbestos handling and temporary restoration, together with removal of the redundant 11kV cable and existing switching station.

Flomar's scope of works

  • Saw cutting, trenching and shoring, including rock excavation
  • Conduit installation, bends and draw ropes, with mandrel testing
  • Stabilised quarry material, backfill and compaction, with compaction testing every 50 m
  • Excavation and installation of precast 33kV joint bays, and entry and exit pits with linking conduits for trenchless crossings; drilling by others
  • Fibre and earth pits, earth link boxes and cross-bond link boxes, and earthing grids for joint bays and link boxes
  • Potholing and non-destructive digging around existing services and tree roots
  • Collection, loading, pulling, installation and sealing of the 33kV, earth and fibre cables
  • Handling of asbestos-containing spoil, waste classification, and cartage and disposal to EPA-approved facilities
  • Temporary restoration of disturbed assets
  • Removal of redundant 11kV cable and the existing switching station

Scope highlights

  • Two 33kV feeders
  • Trenching, conduits and 33kV joint bays
  • Six drum lengths from 570 m to 1,056 m per phase
  • About 4.8 km of cable per phase across the two feeders
  • Removal of redundant 11kV infrastructure

Project register

Principal clientAusconnex
LocationSeven Hills, NSW
StatusCompleted
ValueOn request

Value bands cover Flomar's own package only, never the whole-project figure, and are provided on request.

Project context

Crews installing orange conduits in an open trench at Seven Hills
Orange conduits installed in an open road trench on the SYD08 feeder route
Shored excavation and conduit entries on the SYD08 feeder route
Orange conduits entering an excavated pit on the SYD08 feeder route
Open feeder-route trench and roadside excavation for SYD08
Parallel conduits laid along an excavated section of the SYD08 feeder route
Conduits installed in an excavated section of the SYD08 cable route
Cable drum handling beside the SYD08 feeder route
Crew and excavator working beside an open SYD08 feeder trench

Working out who to put on your next tender?

Tell us the civil and electrical-enabling scope. We will tell you plainly what we self-perform and where we partner.

(02) 9550 0658