Parramatta Light Rail Stage 2 - Enabling Works

A new light-rail connection between Parramatta and Sydney Olympic Park, including a river crossing between Melrose Park and Wentworth Point.

RailPower

Wider-project visualisation supplied by Flomar. This image illustrates the wider project; Flomar's own work is described below.

Principal contractorJohn Holland
Principal clientTransport for NSW
LocationMelrose Park + Wentworth Point, Sydney NSW
StatusIn delivery as at July 2026
SectorRail

Project overview

Parramatta Light Rail Stage 2 will connect Parramatta with Sydney Olympic Park and cross the Parramatta River on a new combined bus and light-rail bridge between Melrose Park and Wentworth Point.

What Flomar self-performs

  • Endeavour Energy 11kV relocation - trenching, cable termination and jointing, pole, pillar and UGOH works
  • Ausgrid LV and streetlight relocation - link pillars, new LED columns and luminaires
  • Polyethylene sleeve supply and installation for the gas network
  • Ausgrid fibre relocation - trafficable pits, splice pits and linking conduits
  • Service proving by electromagnetic and GPR scanning with non-destructive potholing within 5m of the alignment
  • Temporary reinstatement of roads, kerbs, footpaths and verges

Key quantities

  • 4 utility relocation packages
  • HV, LV, streetlight + fibre scope
  • Corridor cleared for a 320m river bridge

Project register

Principal contractorJohn Holland
Principal clientTransport for NSW
LocationMelrose Park + Wentworth Point, Sydney NSW
StatusIn delivery as at July 2026
ValueOn request

Value bands cover Flomar's own package only, never the whole-project figure, and are provided on request.