Skip to content
Visualisation of the Mona Vale Road upgrade

Mona Vale Road Upgrade

ITS cableways, box culverts, headwalls, wingwalls, stormwater pits and sewer-manhole concrete works for the Mona Vale Road Upgrade.

Roads & motorwaysWater, wastewater & drainage
Principal contractorGeorgiou
Principal clientTransport for NSW
LocationMona Vale Road, between Manor Road, Ingleside and Foley Street, Mona Vale NSW
StatusCompleted
SectorRoads & motorways
ProgramDecember 2020 to 2023

Project overview

The Mona Vale Road East Upgrade widened about 3.2km of road from two lanes to four between Ingleside and Mona Vale. It included upgraded intersections, wildlife crossings, retaining and noise walls, rock cuttings, bus priority and shared paths. Transport for NSW was the principal client and Georgiou the principal contractor.

Flomar delivered ITS cableways and minor concrete works as a subcontractor, with additional box culvert, headwall, wingwall and stormwater works for Georgiou. Sewer manhole concrete works were delivered for another contractor on the project.

Flomar's scope of works

ITS cableways

  • Saw-cutting and pavement removal for trenches and road crossings
  • Trench excavation and shoring, including rock excavation
  • 100mm communications and electrical conduits, spacers and marker tape
  • ITS pits and enclosures with labelled brass lids
  • Cement-stabilised sand bedding and backfill, and concrete encasement where required
  • Night-shift road crossings, steel plates and temporary reinstatement
  • Shared trenches with third-party carrier conduits
  • Conduit testing and handling and installation of free-issue materials
  • Sediment control and spoil placement in the designated on-site area

Box culverts, headwalls and wingwalls

  • Installation of precast box culverts, including blinding, base-slab formwork, reinforcement and pour (FRP), dowels, culvert placement, grout and waterproofing tape; permanent materials and craneage by Georgiou
  • Installation of headwalls
  • Formwork, reinforcement and pour of wingwalls

Stormwater network

  • Construction of in-situ pits on the new stormwater network
  • Connections between the new and existing stormwater networks

Minor concrete works

  • Formwork, reinforcement and concrete for cast-in-situ structural drainage pits
  • Pit risers, lintels and kerb connections to stormwater pits

Sewer manholes

  • Formwork, reinforcement fixing and concrete placement over an existing 1050mm sewer main
  • Base slab, walls, soffit and ladder rungs; excavation, blinding and concrete supply by others

Scope highlights

  • About 2,300 m³ of ITS trench excavation and backfill
  • About 6.9 km of communications conduit and 7.0 km of electrical conduit
  • More than 50 ITS pits and at least four structural drainage pits
  • More than 140 m³ of rock excavation
  • Stage 1 culvert base slab: about 14.5 m long and 350 mm thick
  • Sewer-manhole concrete works: about 3 m deep and 16 m³ of concrete

Project register

Principal contractorGeorgiou
Principal clientTransport for NSW
LocationMona Vale Road, between Manor Road, Ingleside and Foley Street, Mona Vale NSW
StatusCompleted
ValueOn request

Value bands cover Flomar's own package only, never the whole-project figure, and are provided on request.

Project context

Visualisation of the Mona Vale Road upgrade
Site photograph of Mona Vale Road Upgrade - view 1
Site photograph of Mona Vale Road Upgrade - view 2
Site photograph of Mona Vale Road Upgrade - view 3
Site photograph of Mona Vale Road Upgrade - view 4
Site photograph of Mona Vale Road Upgrade - view 5
Site photograph of Mona Vale Road Upgrade - view 6
Site photograph of Mona Vale Road Upgrade - view 7
Site photograph of Mona Vale Road Upgrade - view 8
ITS conduit trench on the Mona Vale Road Upgrade

Working out who to put on your next tender?

Tell us the civil and electrical-enabling scope. We will tell you plainly what we self-perform and where we partner.

(02) 9550 0658