Inland Rail Illabo to Stockinbingal - Drainage Package
Precast culverts, pipes, headwalls and drainage installation along the Illabo to Stockinbingal section of Inland Rail in the NSW Riverina.
Project overview
The Illabo to Stockinbingal section adds a new rail corridor through the Riverina as part of Inland Rail, connecting the existing lines near Illabo and Stockinbingal.
Flomar is delivering the stormwater drainage installation for John Holland across six sections between Illabo Junction and Stockinbingal Junction. The drainage package covers about 2km, using precast box culverts, reinforced concrete pipes and HDPE.
Flomar's scope of works
- Install precast reinforced concrete box culverts, reinforced concrete pipes (Class 4) and HDPE lines
- Headwalls, wingwalls and apron slabs with stitch pours joining precast elements
- Localised detail excavation, engineered fill bedding and backfill tying into the earthworks
- Subsoil and subsurface drainage installation
- Dewatering and CCTV testing of drainage components to RMS R11
Scope highlights
- Drainage package covering about 2km
- Six drainage sections between the junctions
- Precast box culverts, Class 4 concrete pipes and HDPE
- Headwalls, wingwalls and apron slabs
- Dewatering and CCTV testing to RMS R11
Project register
Value bands cover Flomar's own package only, never the whole-project figure, and are provided on request.
Working out who to put on your next tender?
Tell us the civil and electrical-enabling scope. We will tell you plainly what we self-perform and where we partner.
(02) 9550 0658